Westhampton NJ Project
Thursday, September 9, 2010
Day 4
Ok, I know what happened to day 2 and 3. Well lets see day two the houses were moving along great with the exception of house 1 and 3. By the end of the day one was still in need of roof sheathing and 3 papering and shingles. Well they were looking for people to stay and paper and start the roof and we all know that's an open invitation for Neil so yes I volunteered us. So Tuesday we got back to the Church at 9:00. Wednesday was a little less eventful for us but house #6 had some issues with the forklift trying to load shingles and breaking a roof truss and almost pulling the the house down. Well it's now 6 am and I need to get moving to the site for a leaders meeting. Oh and by the way Dennis has managed not to get hurt so far!